Poplar River Bridge Replacement
This is a non-designated project on federal lands or outside Canada. The listed authorities are responsible for the project assessment.
Poplar River First Nation (PRFN) requires the construction of a new bridge to facilitate commuting and heavy load transport for the community. The existing Poplar River and Franklin River bridges have existing load restrictions and therefore do not meet community servicing needs. This project will involve the rehabilitation of the Poplar River Bridge to facilitate commuter use, and the Franklin River bridge will be converted to a pedestrian only bridge. A new bridge will be constructed over the Franklin River to service the heavy load and commuting needs of the PRFN community.
The new bridge requires piers to be placed in the water, as a single span structure was not feasible for the community. Temporary rock causeways will be required to drive the pier piles within the channel. All of these works below the high water mark have the potential to impact fish and fish habitat, with the piers resulting in a permanent loss of fish habitat within Franklin River.
Latest update
.
Participate
Key documents
| Document number | Document title | File | Date |
|---|---|---|---|
| 3 | Notice of Determination | - | January 16, 2024 |
| 2 | Public Comment Period on Intent to Make a Determination - Transport Canada | - | November 24, 2023 |
| 1 | Public Comment Period on Intent to Make a Determination | - | September 20, 2022 |
Contacts
Indigenous Services CanadaAngela Bidinosti, Senior Environmental Officer
200-365 Hargrave Street
Winnipeg, Manitoba R3B 3A3
Telephone: 204-984-0964
Fax: 204-983-2936
Email: angela.bidinosti@canada.ca
Transport Canada
Melissa Fraser, Acting Senior Regional Environmental Advisor, Environmental Programs, Prairie and Northern Region
344 Edmonton Street
Winnipeg, Manitoba R3B 2L4
Telephone: 204-227-3329
Email: melissa.fraser@tc.gc.ca
Disclaimer
This map is for illustrative purposes. The markers represent the approximate locations based on available data. More than one marker may be identified for a given assessment.
-
Location
- Poplar River First Nation (Manitoba)
-
Nature of Activity
- Bridges
-
Assessment Status
Completed -
Start Date
2022-09-09 -
Proponent
Poplar River First Nation -
Authorities
- Indigenous Services Canada
-
Assessment Type
Project on federal lands -
Reference Number
83983
Nearby assessments
...within 200 kilometres-
New (Multiple) and Upgrades (Multiple) Radiocommunications Towers
Poplar River -
Teacherages Project (Site Servicing)
Poplar River First Nation -
Project 4 - All-Season Road Connecting Berens River to Poplar River First Nation
-
New Tower Construction, Upgrade single tower & New Fibre Installation
Project site 1: Poplar River 16 Tower 1 -
New Tower Construction, Upgrade single tower & New Fibre Installation
Project site 2: Poplar River 16 Tower 2 -
Poplar River First Nation School
Poplar River Manitoba School -
Modification to Poplar River First Nation Radiocommunication Tower at Poplar River, MB
Poplar River -
Poplar River First Nation - Community Wharf
Poplar River First Nation -
Poplar River First Nation Lagoon Expansion
Poplar River First Nation -
Poplar River - Harbour Improvements
Poplar River -
Poplar River Harbour Manitoba - Routine Maintenance Dredging of the Poplar River at Lake Winnipeg - Winter 2019
Poplar River Harbour -
Poplar River First Nation Water Treatment Plant
Poplar River First Nation -
Wharf Demolition and Reconstruction - George Island, MB - Summer 2020/Winter 2021
George Island Harbour -
New (Multiple) Tower Construction or Upgrade & New Fibre Installation
Project site 6: BCN-BRR-TW3 -
Berens River Small Craft Harbour Breakwater Repairs and Pile Installation
Berens River - Sigurdsson Island Small Craft Harbour -
Berens River Harbour Launch Ramp Reconstruction
Berens River Small Craft Harbours -
Harbour Improvements - Berens River - Sigurdsson Island, MB
Berens River -
New (Multiple) Tower Construction or Upgrade & New Fibre Installation
Project site 4: BCN-BRR-TW1 -
New Tower Construction, Upgrade single tower & New Fibre Installation
Project site 3: Berens River 13 -
Berens River Water Treatment Plant Upgrade
Berens River First Nation -
Berens River First Nation Road Upgrades
Berens River -
Berens River Bridge Replacement
Berens River First Nation -
New (Multiple) Tower Construction or Upgrade & New Fibre Installation
Project site 5: BCN-BRR-TW2 -
Project 4 - All-Season Road Connecting Berens River to Poplar River First Nation
East side of Lake Winnipeg, between Poplar and Berens Rivers -
Chief Elsie Bouchie Culture Camp
Pigeon River 13A -
McBeth Point Harbour Improvements
McBeth Point Harbour -
Berens River 13 Rapid Housing Fourplexes
Berens River 13 -
Rossville Small Craft Harbour Improvements
Rossville (Mission Island) Small Craft Harbour -
Norway House Cree Nation School Renovation and Playground CSC28
Norway House Cree Nation -
Norway House Cree Nation Water Intake Replacement and Lagoon Cell Decommissioning
Norway House Cree Nation -
New Tower Construction, Upgrade Towers & New Fibre Installation
Project site 1: Norway House Cree Nation -
Norway House Cree Nation Business Center
Norway House Cree Nation -
Norway House Dock Removal
Norway House -
ENV - 268 - EA - ERP - Kinonjeoshtegon - CHRT 41 - JP New Building and Renovation - P057361 - 2425
Kinonjeoshtegon First Nation -
New Fibre Installation - Dauphin River
Project site 1: Anama Bay -
Dauphin River Small Craft Harbour Dredging and Pile Installation
Dauphin River Small Craft Harbour -
Dauphin River Harbour Manitoba - Routine Maintenance Dredging of the Dauphin River at Lake Winnipeg - Winter 2019
Dauphin River Harbour -
Lake Manitoba and Lake St. Martin Outlet Channels Project
Lake St. Martin Outlet Channel outlet on Lake Winnipeg -
Misipawistik Cree Nation Cultural Centre
Grand Rapids -
Misipawistik Cree Nation Cultural Centre
Misipawistik Cree Nation -
Misipawistik - CHRT41 - P053203 - Phase 2 JP Project - 2324
Misipawistik Cree Nation -
New Fibre Installation
Grand Rapids (Misipawistik Cree Nation) -
Misipawistik Cree Nation - Water Treatment Plant Upgrade and Expansion Project
Misipawistik Cree Nation -
Bell MTS Radiocommunication Tower on Bloodvein Reserve No. 12
Bloodvein Reserve No. 12 -
New (Multiple) and Upgrades (Multiple) Radiocommunications Towers
Bloodvein -
New (Multiple) Tower Construction or Upgrade & New Fibre Installation
Project site 1: BCN-BLD-TW1 -
Bloodvein First Nation Environmental Remedial Actions - 5 PHC Sites
Bloodvein First Nation -
Bloodvein First Nation CFS Prevention Building
Bloodvein First Nation -
Bloodvein First Nation Staff Housing
Bloodvein First Nation -
Bloodvein River Airport Wildlife Fencing
Bloodvein River -
Bloodvein First Nation Environmental Remedial Actions - 5 PHC Sites
Bloodvein First Nation -
Bloodvein First Nation Environmental Remedial Actions - 5 PHC Sites
Bloodvein First Nation -
Bloodvein First Nation Environmental Remedial Actions - 5 PHC Sites
Bloodvein First Nation -
Bloodvein First Nation School
Bloodvein School -
Bloodvein First Nation Environmental Remedial Actions - 5 PHC Sites
Bloodvein First Nation -
New (Multiple) Tower Construction or Upgrade & New Fibre Installation
Project site 2: BCN-BLD-TW2 -
New (Multiple) Tower Construction or Upgrade & New Fibre Installation
Project site 3: BCN-BLD-TW3 -
Lake Manitoba and Lake St. Martin Outlet Channels Project
Lake St. Martin Outlet Channel inlet on Lake St. Martin -
Pauingassi First Nation Child and Family Services Prevention Building and Staff Housing
Pauingassi First Nation -
Lake St. Martin - Water Treatment Plant Zebra Mussels Control
Lake St. Martin -
New Fibre Installation - Dauphin River
Project site 2: Obushkudayang Indian Reserve -
Little Grand Rapids Submarine Cable Installation Project
Little Grand Rapids -
Aboveground Fuel Storage Replacement in Little Grand Rapids, Manitoba
Little Grand Rapids -
Launch Ramp Reconstruction - Calders Dock, MB - Fall 2021
Calders Dock Harbour -
Little Grand Rapids Dock & Dock Foundation Posts
Little Grand Rapids -
Little Grand Rapids RCMP New Living Quarters
Little Grand Rapids -
Southeast CFS Little Grand Rapids Staff Housing (Personnel and Visiting Professionals) and Prevention Centre
Little Grand Rapids First Nation -
Little Grand Rapids First Nation School
Little Grand Rapids First Nation School -
Little Grand Rapids First Nation Transitional Housing (Temporary Housing)
Little Grand Rapids First Nation -
Launch Ramp Reconstruction - Whiskey Jack Portage, MB - Fall 2021
Whiskey Jack Portage -
Chemawawin Cree Nation Water Treatment Plant Project
Chemawawin Cree Nation -
Little Saskatchewan First Nation - Mino-Aya-Win Centre
Little Saskatchewan First Nation -
Chemawawin Cree Nation Transitional Housing Building
Chemawawin Cree Nation -
Easterville Harbour Wharf and Launch Ramp Reconstruction
Easterville, Manitoba -
Fisher River Cree Nation East Road Replacement Project
Fisher River Cree Nation Reserve no. 44 -
Fisher River Cree Nation Jordan Principle Building
Fisher River Cree Nation -
Fisher River Used Oil Burner Installation
Fisher River Cree Nation -
Wasagamack First Nation Leachate Management Upgrades (Engineered Wetlands) - 2021
Wasagamack First Nation -
Cross Lake Band of Indians - 14 Portable Classrooms
Cross Lake Band of Indians -
Hydrometric Station Decommissioning - Fisher River, Manitoba
Fisher River, Manitoba -
Pinaymootang First Nation Water Treatment Upgrades
Pinaymootang First Nation -
STPFN Wastewater Treatment Plant Upgrade and Expansion Project
St. Theresa Point First Nation -
New Nursing Station
Wasagamack First Nation -
CLCOI Road B Sewer and Water
Cross Lake Band of Indians -
Wasagamack - Fuel Tank Relocation - 2324
Wasagamack Fuel Tanks -
Cross Lake Band of Indians - Nikan Awasiska Agency Administration Office & Site Development
Cross Lake -
St. Theresa Point First Nation - Old Bulk Fuels Decommissioning
St. Theresa Point First Nation -
Cross Lake Women's Shelter
Cross Lake Women's Shelter -
Cross Lake Band of Indians Wastewater Lagoon Upgrade
Cross Lake -
New (Multiple) Tower Construction, Upgrade (Multiple) Towers, and New Fibre Installation
Project Site 06: Island Lake region - Wasagamack Band Office -
New (Multiple) Tower Construction, Upgrade (Multiple) Towers, and New Fibre Installation
Project Site 14: Island Lake region - Theresa Point Band Office -
New Fibre Installation
Project site 1 - Cross Lake First Nation -
Cross Lake Band of Indians - CHRT41 - Jordan Principle Building
Cross Lake Band of Indians -
Cross Lake Youth Centre
Cross Lake Band of Indians -
St Theresa Point Northern Store Contamination Remediation
St Theresa Point Former Bulk Fuel Plant -
STPFN Wastewater Treatment Plant Upgrade and Expansion Project
St. Theresa Point First Nation -
St Theresa Point First Nation road re-construction
St Theresa Pt First Nation -
Sugar Creek Peat Harvesting Project
Fisher River Cree Nation -
Lake Manitoba and Lake St. Martin Outlet Channels Project
Lake Manitoba Outlet Channel outlet on Lake St. Martin -
Peguis First Nation Recreation Centre Soil Remediation
Peguis First Nation Recreation Centre Soil Remediation -
New Peguis First Nation Radiocommunication Tower in Peguis, MB
Peguis, MB -
Xplornet Communications Inc. Radiocommunication Antenna Addition on Peguis First Nation Reserve No. 269
Peguis First Nation Reserve No. 269 -
Wharf Reconstruction - Little Grindstone, MB - Winter/Spring 2020
Little Grindstone Harbour -
Skownan New Child and Family Services Prevention Building
Skownan First Nation -
NAV CANADA Radiocommunication Antenna Addition in Island Lake, MB
Island Lake Tower 3, MB -
NAV CANADA Radiocommunication Antenna Addition in Island Lake, MB
Island Lake Tower 2, MB -
NAV CANADA Radiocommunication Antenna Addition in Island Lake, MB
Island Lake Tower 1, MB -
Skownan First Nation Waste Site Closure and Eco-Depot Facility
Skownan First Nation -
New (Multiple) Tower Construction, Upgrade (Multiple) Towers, and New Fibre Installation
Project Site 22: Island Lake region - Garden Hill Band Office -
Aboveground Fuel Storage Replacement in Island Lake, Manitoba
Island Lake -
Garden Hill First Nation Road Upgrades
Garden Hill